Thursday, August 1, 2013

Minutes of the Trustee Meeting
Queensberry Condominium Trust
July 23,  2013


Pursuant to the Article V.  Section 5.9 of the By-Laws of Queensberry Condominium Trust, a monthly meeting of the Trustees was held on Tuesday, July 23, 2013, at 6:30PM at the offices of Boston Choice Properties, 125 Jersey Street, Boston, MA.


Those Present:  Ning Hernandez and Jeff Schwarz , Trustees
Sheryl Kelly participated via telephone
David Sherf  and Michael Grappo were not present


Pamela Pendias , Modica Associates  


The meeting was called to order at 6:40PM.   


FINANCIAL REVIEW



The June financial report was sent out electronically in advance of the meeting.  The balance sheet as of June 30, 2013,   reflects $8,722 in the operating account and $67,519 in reserves.    With the exception of one unit owner, everyone is current with their condo fees.   As of June 30th, 2013  the association has a net profit of $2,267 for the month and a net profit of $3,194 thus far six months through the fiscal year.   The association is current with all operating bills.    


OLD BUSINESS/MAINTENANCE ISSUES   



Dumpsters on site – The addition of an extra (2) yard container has alleviated the trash over flow issue.   Sheryl noted that the area under the dumpsters is not consistently clean and often times there is debris caught behind and under the containers.   Pam stated she would speak with the maintenance crew concerning this.


It was noted that often times, trash is found mixed in with the recycling containers.   Pam suggested circulating a memo but the consensus of the trustees was that a memo would not do any good.   It was suggested that we simply discontinue recycling altogether but Pam stated that would result in the City curtailing trash pick up that would result in the association having to pay a private trash removal company.    Thus far the building has not be cited for recycling violations and the City has been emptying the containers.     


The vendor needed to have the carpet sent out to be bound in order to finish laying the carpet on the stairs.   Jeff noted that the carpet was being installed differently on the stairs and was not pleased stating that there was no edge exposing the wood stairs.   Pam questioned this since the carpet was being sent out to be bound to allow for this.    The carpet installer advised that the installation should be complete by Friday, July 26th.   The association has not paid any monies as a deposit for the carpet.  


Signs “Please Keep Gate Closed: have now been put on all gates.   Ning and Jeff believe they have made a difference.   


NEW BUSINESS


The association has a new landscaping company this year, Green Pea Urban Gardens.    Although this vendor will probably cost more money than the budget allows, Pam will work with the vendor to keep down the costs.   Pam suggested  that the trustees may want to consider purchasing some perennials, that would be an investment since they would come up year after year and add some color to the garden.   The trustees agreed to allow Peggy


Minutes of the Trustee Meeting
7-23-13
Page Two


Prentice to purchase  perennials of her choice, to embellish the garden at a cost not to exceed $300.



MISCELLANEOUS OTHER BUSINESS


Pam told the trustees that she had recently received Final Notice from the Water Department regarding the lack of a back flow prevention device in building 107.    Ning and Jeff did not recall this being discussed.   Pam stated that she had sent the trustees the original notice when the building was cited in May.    Sheryl checked her old e-mails and found that the trustees were notified of this requirement .    Pam told the trustees that this would be costly and would obtain estimates.


On a positive note, the vandal responsible for breaking the glass in the door in the spring will be reimbursing the association $600, for the cost the association incurred for cleaning up the glass on the weekend and replacing it.  The courts indicated that the defendant must repay the sum in six months.                 


There being no further business, the meeting adjourned at 7:10PM.  


Respectfully submitted by:
Pamela Pendias
Modica Associates
For the Recording Secretary
Queensberry Condominium Trust

Thursday, June 13, 2013

Minutes of the Trustee Meeting
Queensberry Condominium Trust
May 29,  2013

Pursuant to the Article V.  Section 5.9 of the By-Laws of Queensberry Condominium Trust, a monthly meeting of the Trustees was held on Wednesday, May 29, 2013, at 6:30PM at the offices of Boston Choice Properties, 125 Jersey Street, Boston, MA.

Those Present:  Michel Grappo , Ning Hernandez, Sheryl Kelly and Jeff Schwarz , Trustees
David Sherf were not present
Pamela Pendias , Modica Associates 
The meeting was called to order at 6:35 PM.  

FINANCIAL REVIEW


The April financial report was sent out electronically in advance of the meeting.  The balance sheet as of April 30, 2013,   reflects $4,080 in the operating account and $64,804 in reserves.    With the exception of one unit owner, everyone is current with their condo fees.  

Due to the meeting taking place very late in the month,  Pam furnished the trustees with a balance sheet as of May 29th, after all bills had been paid, reflecting $5,980 in operating and $64,804 in reserves.    The owner of the delinquent unit has listed the property for sale so the association will be receiving the aging receivable amount of $2,665.    The association has no aged payables and the reserve account has been funded in accordance with the budget. 

OLD BUSINESS/MAINTENANCE ISSUES  


Dumpsters on site – the association purchased an additional dumpster and had another dumpster repaired.    The area seems to be much cleaner.    The addition of an extra (2) yard container has alleviated the trash over flow issue.

Self-Closing Mechanisms for (3) rear gates.    (3) different lock companies were approached regarding the installation of a self-closing mechanism to ensure that these gates are closed and locked.    More often than not the gates are left wide open.    All (3) companies indicated that it would be expensive and require an iron worker to weld something on to the gate so the door closer could be mounted.    Since the closer would be exposed to the elements, there would be no warranty or guarantee on the work performed.    The trustees agreed to abandon the idea of a door closer and requested that signs be mounted on the gates stating “please keep gate closed” as an alternative.

Carpet Installation – the trustees have made a carpet selection,  Patcraft Famous Last Words II #IO147 Results May Vary # 47500.   The carpet has been ordered and will be installed shortly.   The vendor, Bradford Carpet, has indicated that he will need to apply “levelastic” to the cracks in the concrete that will add an additional $800 to the cost of replacing the carpet.    One of the trustees expressed  concern with the hallway in building 107 that leads down to the laundry.    It was decided that the trustees walk over after the meeting and evaluate the situation.   Modica is also obtaining a proposal from a contractor to better level the floor in this area.   Once received it will be forwarded to the board so a decision can be made and the carpet installed. 

NEW BUSINESS

There had been discussion about replacing the mailboxes.    Pam provided (2) proposals to replace mailboxes in both buildings.  Total Security $3,723.75, SRV $4,363.88.     The consensus of the trustees was that it was too costly a project to entertain.   

Minutes of the Trustee Meeting
5-20-13
Page Two

The last order of business was Landscaping.    Both Ning and Sheryl were in favor of accepting the proposal furnished by Peggy Prentice of GreenPea Urban Gardens.    Jeff noted that total outlined in the proposal exceeds the budget allocated for landscaping.     Pam to work with Peggy to work within the budget.     Sheryl reminded Pam to follow up with Peggy on her offer plant the urns out front at no cost to the association due to the length of time it took to obtain the proposal.

Michael Grappo stated that he would not be able to meet on Monday’s during the summer.    The next board meeting will be Monday, July 15th, 2013.  

There being no further business, the meeting adjourned at 7:30PM. 

Respectfully submitted by:
Pamela Pendias
Modica Associates
For the Recording Secretary

Queensberry Condominium Trust

Tuesday, April 20, 2010

March 16 Meeting

Attending:
Corinne Getchell (MA) --Modica Associates
Yelena Chigirinskaya (YC) --Trustee, Queensberry Condominium Trust
Douglas McClennen (DM) --Trustee, Queensberry Condominium Trust
Bill Gentz (BG) --Trustee, Queensberry Condominium Trust
Ning Hernandez (NH) --Trustee, Queensberry Condominium Trust

Distribute to:
David Sherf (DS) --Trustee, Queensberry Condominium Trust
107 Mail Room for general information
111 Mail Room for general information

Second Means of Egress
Item complete.

Window Replacement
The unit (111-2) has the correct panning. MA to send another letter to Hadco to demand the rest of our money. What can we do to prevent this situation from happening in the future? --In the future we will only reimburse owners for window panning once the work is complete and the panning is to spec.

107 Laundry Room Floor
We had bids from multiple places: Vogt & Company (wood floor), and Capuccio Construction (bid for mud floor after we provided the spec, recommended by Dave Modica).

Capuccio Construction bid included adding a layer of concrete onto the foundation, tile on top of that (as opposed to laying tile on an elevated floor), as well as removing the wall behind the washing machine, and replacing it with a water resistant green dry wall. When the wall is removed, Dave Modica and the plumber will inspect the plumbing and electrical hook ups behind that wall.

MA to request a reference for Capuccio before the next meeting.

Consider moving the vent such that the hot air does not blow on the Emerald Arborvitae.

Deformation Monitoring Points (DMPs)
The board wants to have all the DMPs checked this year (both the new and the old ones), and afterwards the board wants to have all the DMPs checked every two years. Item complete.

Torn carpet in basement
A patch was added. Item complete.

Landscaping
Malkasian provided a bid for mulching ($800) and for maintance ($1320), which is in our budget. Beyond maintenance, no landscape improvements can be made right now because the association has no money. The board will meet with the landscaper in April to decide what new plantings to make so that the landscaping work can start once the funds become available.

Terrazzo Sidearms Need Repairs
MA needs to find companies that do casting within 6 months. DM suggests to make a simple repair for now just so that there is no big gash. Might get a year out of the patch. In 2001 it was about $20,000 to do both buildings side arms. For the patch, it will be impossible to get the same aggregate. MA to get a price from a mason for the patch.

Water Damage/Leaks Due to the March 15 Storm
Multiple units have water damage from leaks from 3/15/2010 Noreaster. Units involved are 107-5, 107-10, 107-15, 107-18. Another unit in 107 has damage around the door (unit 107-?). The side of the door this unit is sheared, so there is possible serious structural damage. The contractors were working on it on 3/16/2010 already. They should take out a part of the wall above the unit door to see if there is more structural damage. MA will do the walk through with a mason and the roofer to assess the damage and to determine the cost to fix, and to see if the cost to fix will be over $15,000.

Repolishing Wood on the Front Doors
Polishing the front doors (note that this is not the same as restoring the lobby) has been put on hold due to low cash flow. Modica has previously received several bids for this work. One high end bid was for ~$3600 per door; another bid from Summer Painting was ~$850 per door.

Miscellaneous:

  • A work order for the lentil sitting in courtyard was issued to be moved to the boiler room. Please let MA know if the lentil is still in the courtyard.
    Lentil is still in the courtyard.
  • 111-11 has a AC unit that is in too early. MA to send a letter to the owner.
  • MA to check if there is any money from the city available for dealing with the building settling due to the ground water issues.
Agenda for April:

  • Brainstorm the capitol repairs. Wish list for the capitol repairs to be done by June.
  • Brainstorm ways to raise income for the association (e.g. increasing fine fees, etc.)

These minutes are written to Yelena’s best recollection. Please notify her of any discrepancies immediately.

Wednesday, September 16, 2009

September 15 Meeting

Attending:
Corinne Getchell (MA) --Modica Associates
Yelena Chigirinskaya (YC) --Trustee, Queensberry Condominium Trust
Douglas McClennen (DM) --Trustee, Queensberry Condominium Trust
Bill Gentz (BG) --Trustee, Queensberry Condominium Trust


Distribute to:
Kristen Lipstreuer (KL) --Trustee, Queensberry Condominium Trust
David Sherf (DS) --Trustee, Queensberry Condominium Trust
107 Mail Room for general information
111 Mail Room for general information

Second Means of Egress
Logan Grates has been given the go ahead and is in the process of making the grates. They will be in touch with MA when the grates are ready for installation.

Window Replacement
MA sent another letter to Hadco Window and Door on 9/3, but has not had a reply.

107 Laundry Room Floor
Vogt & Company (the carpentor/vendor whose proposal the association is considering) warns that roll-out/linoleum type floor is pourous, and if there are leaks, the floor maybe severely damaged or destroyed. The carpenter discussed the issue with Dave Modica, and both recommend installing tiled floor. DM estimates that the price difference between tile and linoleum may be over $1000, and the linoleum floor should last for several years. MA to get an estimate on both tile floor and linoleum floor to see what the actual cost may be and what the actual difference in price is. Plumbing is to be inspected when the floor is removed. DM requests that the material to be used for the subfloor is specified in the proposal.

Deformation Monitoring Points (DMPs)
Work has been completed. MA has the report, and the board has reviewed it. MA to ask David Modica to determine when the next time should be for checking the DMPs--two years, or possibly 6 months/1 year for the new DMPs.

2008 Financials
DM would like the cash flow report, sent out to the owners, to show clearly why the association experienced the net loss even though the income from the temporary fee increase collected more money than required for the masonry repairs. DM will email the changes to MA, and MA will mail the information to the owners.


Jim, BG and Corinne will work together to correct the 2009 cash flow report, but will not hold up the mailing to the owners for that.

Torn carpet in basement
Same.

Landscaping
The proposal has been submitted to MA for the board to review. Currently, one Emerald Arborvitae plant in front of the 107 laundry vent is not healthy, probably due to vent, so replacing it, as the proposal suggests, will not resolve the issue. MA to ask the landscaper how that problem can be resolved.


The cost of the materials and labor proposed is $2000. Due to lack of finances to do this work right now, MA to ask the landscaper if the work can be postponed till next spring.

111 Laundry Sink Tap Is Leaking
The threads on the tap are stripped, so the facet handles have to be replaced. Dave Modica estimates the cost to be $200-$250.

Terrazzo Sidearms Need Repairs
107 sidearms are crumbling and falling apart. 111 sidearms also have problems, but are not in as bad shape as 107.


Miscellaneous:
  • Extra lentil sitting in the courtyard. MA to ask Chicorelli about it. It should probably not be left there, and should at least be moved down to the boiler room for safe storage.
  • Outer door glass been broken in 107. The glass needs to be replaced.
  • Front doors needs polish

These minutes are written to Yelena’s best recollection. Please notify her of any discrepancies immediately.

Monday, September 14, 2009

August 18 Meeting

Attending:

Corinne Getchell (MA) --Modica Associates
Yelena Chigirinskaya (YC) --Trustee, Queensberry Condominium Trust
Douglas McClennen (DM) --Trustee, Queensberry Condominium Trust
Bill Gentz (BG) --Trustee, Queensberry Condominium Trust

Distribute to:
Kristen Lipstreuer (KL) --Trustee, Queensberry Condominium Trust
David Sherf (DS) --Trustee, Queensberry Condominium Trust
107 Mail Room for general information
111 Mail Room for general information


Second Means of Egress
Samples have been delivered to Modica, and the board approves the samples. MA to call and schedule the installation.

Window Replacement
Same.

107 Laundry Room Floor
Carpenter (Vogt & Company) did a proposal and submitted to MA, with the cost of $7600. The proposal includes carpentry, but does not include tiling, removing and reinstalling the washing machines. The laundry company will have to do the removal and reinstallation of the machines. The laundry company will not give the association more than $700-800. The estimate is approximately $52.77/sq. foot (based on 8x18 ft area).

Doug proposes to just fix the floor, and put down rolled goods. Currently the floor is a potential tripping hazard.

MA to ask the carpenter to price items 1-3 on the proposal, without preparing the floor for tiling (described in item 2), without new cabinets or counters, and without painting.

When the floor is lifted, it is likely that they will find rot in the joices. Joices will have to be replaced. This work would not be included in the estimate.

Deformation Monitoring Points (DMPs)
Doug spoke to Cullinan Engineering. We did not lose a lot of information. The work is not completely redundant. The measurements have to be done 3 times due to temperature variances. They have to do it 2-3 times to get an accurate measurement. Cullinan will invoice one time once the work is completed. The board approves the proposal. MA will contact Cullinan Engineering to proceed.

Bad smell in 107
Doug and Bill have not noticed the bad smell for awhile. Item complete.

2008 Financials
Bill met with MA’s accountant and redid the summary for 2008. Transfer from reserve and other expenses items have been cleaned up, and the totals have changed as a result. Bill proposes to add footnotes when the new financial summary is sent to the owners. MA will put the new financial summary in a digestable form for the owners. Bill created a summary of income and expenses for the masonry project. The following will be mailed to the owners: reconciliation of 2008 financial summary with the footnotes, the masonry project summary, and trustee voting forms.

Torn carpet in basement
Same.

Landscaping
The landscaper is still working on the proposal.

Security cameras
Doug did some investigation on the cameras, and found that the association can get 5 WiFi cameras for about $500. Anyone can access the cameras if he/she knows the IP address and the password. The ongoing cost would be electricity and IP address. This is not a high priority, so the item will be moved to the Long Term projects list. This project may be coupled with redoing the front doors.

111 Laundry Sink Tap Is Leaking
Same.

These minutes are written to Yelena’s best recollection. Please notify her of any discrepancies immediately.

Wednesday, June 24, 2009

June 16 Meeting

Attending:

Corinne Getchell (MA) --Modica Associates
Douglas McClennen (DM) --Trustee, Queensberry Condominium Trust
Bill Gentz (BG) --Trustee, Queensberry Condominium Trust
David Sherf (DS) --Trustee, Queensberry Condominium Trust

Distribute to:
Yelena Chigirinskaya (YC) --Trustee, Queensberry Condominium Trust
Kristen Lipstreuer (KL) --Trustee, Queensberry Condominium Trust

107 Mail Room for general information
111 Mail Room for general information

Second means of egress

Waiting on second sample for approval.

107 laundry room floor

Modica to get bids for new floor and investigate installation of back flow valve.

Deformation Monitoring Points (DMPs)

Doug will call Cullinan to clear up questions concerning new work. Will give Corrine a call to move ahead with work if satisfied with responses.

Bad smell in 107
Smell has lessened to a large degree, but longer term a back-flow valve need to be installed

Dead Tree in Front of 107
New tree planted. Item Complete.

2008 Financials

Suggestion that statements include a current balance sheet that reflect actual assets puchased by the trust beside just cash. Still waiting for final balance on exterior work.

Torn carpet in basement
Same.

Landscaping
Still waiting on proposal.

Security cameras
Doug to investigate WiFi camera.

111 Laundry Sink Tap Is Leaking
Have asked that plumber move sink valve handles to 9 and 3 o'clock.

These minutes are written to Doug’s best recollection. Please notify her of any discrepancies immediately.

Wednesday, June 3, 2009

May 19 Meeting

Attending:
Corinne Getchell (MA) --Modica Associates
Yelena Chigirinskaya (YC) --Trustee, Queensberry Condominium Trust
Douglas McClennen (DM) --Trustee, Queensberry Condominium Trust
Bill Gentz (BG) --Trustee, Queensberry Condominium Trust

Distribute to:
Kristen Lipstreuer (KL) --Trustee, Queensberry Condominium Trust
David Sherf (DS) --Trustee, Queensberry Condominium Trust
107 Mail Room for general information
111 Mail Room for general information

Structural Needs Assessment Report
All items listed by the independent engineer's report have been repaired. So Chicarelli & Pires was paid the remaining $10,000 on April 29. Item Complete.

Second Means of Egress
Logan Grates began installation, but MA realized that a wrong type of grate was being used. Logan Grates will provide another sample for approval before installing.

Window Replacement
Same.

107 Laundry Room Floor
MA is continuing to negotiate with ALS (Automatic Laundry Services). $750 that ALS has agreed to give to the association to fix the floor is not enough. MA will ask ALS if ALS knows anyone who would do that kind of work for only $750, or try to negotiate a larger amount. When the floor is removed, the plumbing underneath needs to be investigated. It is possible that the smell in 107 is caused by drain water backing up. One suggested solution is to install a backflow preventor.

Bad Smell in 107
The smell has been cleared for now. The city has cleared out the sewers. Will monitor to see if the smell returns.

Dead Tree in Front of 107
Same. Doug has offered to purchase a ginko tree. The landscaper (Malkasian) provided an estimate of $250 that includes installation of the tree only. (The amount is higher because the stump of the old tree has to be dug out.) MA to ask Malkasian for the total estimate on purchase, delivery and installation of the tree.

Torn Carpet in the Basement
Dave Modica is investigating.

2008 Financials
Bill is working with Modica's accountant to reformat the monthly financial statements to make them easier to understand. Bill and Doug are also working to reorganize the financials for mailing out to the owners. So far the following problems have been identified: 1) balance sheets need to match the assets; 2) certain column items are superfluous and can be removed from the budget comparisons; 3) bank statements do not reflect the cut checks that have not yet been cached by the payee.


Landscaping
Doug and Corinne met with Rick Malkasian. The association plans to use $1500-$2000 this year (in addition to what is normally allocated for landscape maintenance) to plant and fix landscaping starting from the Queensberry Street alley to Jersey St. The trustees are now waiting for a specific proposal. MA to ask the landscaper about the timeframe.
NOTE: The tree in front of 111 Jersey needs to be pruned--it is too low to the ground. It also needs to be treated. MA to speak to an arborist about treatment.

Deformation Monitoring Points (DMP's)
Cullinan Engineering provided an estimate to create 7 new Deformation Monitoring Points (DMP's) to replace the ones destroyed during the masonry and structure works, set the baseline for the new points, and do a regular reading on all 37 points for $4275. Previously, the association has been paying approximately $2000 for reading and computation. The last reading was taken in February, 2007. Trustees have questions on the work proposed by Cullinan Engineering. On point 2 in the estimate proposal—does this imply 2 separate readings? How far apart will the readings be? If the readings are done at the same time, then why do we need 2 readings done? On point 3 in the estimate proposal—would this be the 3rd time readings are taken on the 7 new DMPs? How will this be billed?


111 Laundry Sink Tap Is Leaking
MA plumber has looked at the leak, but the tap is still leaking. Also the faucet handle shut off position is too close to a hose.

Security Cameras
A system can cost anywhere between $4000 and $15000. Some of the variables are whether the system is digital; how an incident is handled; who would review the recordings. Once a system is installed the options are to sign up for a maintenance plan or to pay a fee to review the recordings when an incident occurs. Further investigation of cameras installation will be put on hold until the 107 laundry room floor issues are resolved.

Misc:

  • The glass in the 111 Jersey entry door has recently been broken and replaced 3 times. The glass cost approximately $370 per door
  • Regular carpet cleaning was done

These minutes are written to Yelena’s best recollection. Please notify her of any discrepancies immediately.

Thursday, March 19, 2009

March 17 Meeting

Attending:

Corinne Getchell (MA) --Modica Associates
Yelena Chigirinskaya (YC) --Trustee, Queensberry Condominium Trust
Douglas McClennen (DM) --Trustee, Queensberry Condominium Trust
Bill Gentz (BG) --Trustee, Queensberry Condominium Trust


Distribute to:
Kristen Lipstreuer (KL) --Trustee, Queensberry Condominium Trust
David Sherf (DS) --Trustee, Queensberry Condominium Trust
107 Mail Room for general information
111 Mail Room for general information


Structural Needs Assessment Report
An independent engineer provided a report on the masonry work. In general everything was done well. Dave Modica will review the report and email the board his comments. The report points out a few oversights (e.g. page 10, photo 6, shows that the 111 Jersey entrance cornice has not been repaired). Chicarelli & Pires was paid all except $10,000. MA will continue to withhold the $10,000 until the items pointed out by the independent engineer’s report are fixed.
MA to check on when we last looked at the building settlement points.

Second Means of Egress
Same.

Window Replacement
Still waiting on refund from Hadco. Logan Grates will fix the grids.

107 Laundry Room Floor
ALS (Automatic Laudry Services) came and looked at the floor. ALS will give us $750 to fix the floor. When the floor is removed, we will need to investigate the drain pipes underneath to see if larger pipes have to be installed.
Our contract with ALS does not expire until 2014. Laundry breakdown: 55% to ALS, 45% to QCT.


Bad Smell in 107
The smell is still there, but not as bad. In February, John’s Sewer snaked the main sewer line in 107. The line has a few dips where water holds and at 83 feet line is possibly rotted at bottom. Also the 3 stacks on the roof were video inspected. The stack on the right has a small hole at about 48 ft from the room. Clean out is at 51 ft (white color). Doug inspected the Is the hole in the stack a possible cause of the smell, and can the hole be fixed? Inquire the drain companies. MA to ask Dave Modica and a plumber take a look and provide feedback on the video? Inquire about the possible rotted sewer line. After reviewing the video, DM thought that the middle pipe might also not be draining properly and maybe the cause of the smell.


Dead Tree in Front of 107
Same.

Torn Carpet in the Basement
AJ Rose Carpets will look at the problem this week. MA to ask them for a recommendation to possibly tear out that section of the carpet and replace it, or cover it with a “throw” type carpet matt.

2008 Financials
Bill is working with Modica's accountant to straighten out and simplify our financials. MA to send out the trustee ballots to the owners by mail (no quorum at the annual meeting), together with the financials in about two weeks.

Landscaping
The board is again reviewing the landscape design.

These minutes are written to Yelena’s best recollection. Please notify her of any discrepancies immediately.

Wednesday, February 18, 2009

January 20 Meething

Attending:
Corinne Getchell (MA) --Modica Associates
Douglas McClennen (DM) --Trustee, Queensberry Condominium Trust
David Sherf (DS) --Trustee, Queensberry Condominium Trust
Bill Gentz (BG) --Trustee, Queensberry Condominium Trust
Distribute to:
Kristen Lipstreuer (KL) --Trustee, Queensberry Condominium Trust
Yelena Chigirinskaya (YC) --Trustee, Queensberry Condominium Trust
107 Mail Room for general information
111 Mail Room for general information

2008 Finances
Corrine will have final numbers for Feb meeting. Bill asked for copies bank statements for the full year 2008.

Structural Needs Assessment Report
Nothing further on Lentil on exit at 111. Dave to meet with engineer Thursday Jan 22nd. Bill asked that engineer give his general impressions of the condition of the building.

Second Means of Egress
Grates are finished but Logan grate needs access to units to install. Corrine will schedule.

Damanged Bollards by the Dumpsters
Item Complete.

Window Replacement
Window Paining has been repaired. Waiting for Logan grate to reinstall.

107 Laundry Room Floor
Proposal by DM to motion at owners meeting that we consider reconfiguring entire space including storage locker area and boiler room to be more efficient. Including replacing current inefficient gas systems. Will ask owners for feed back on whether to hire engineer to make proposal.

Dead Tree in Front of 107
Same.

Bad Smell in 107
Smell still occurring occasionally. DM mentioned that ventilation in skylight is not working and needs to be addressed.

Issues in the Monthly Financial Statement
Item Complete.

Moped in the Courtyard
Removed. Item Complete.

Torn Carpet in the Basement
Corrine to call Braintree rug to look into replacing torn rug in basement.

Miscellaneous
  • DM sent email regarding installing security camera
  • DM asked to have Feb Trustee meeting scheduled for 24th instead of 17th
    These minutes are written to Douglas’s best recollection. Please notify her of any discrepancies immediately.

Tuesday, November 18, 2008

Torn Carpet In The Basement

(11/18/2008) Carpet is shredded across from Unit 20-A, probably from the vacuum cleaner.

(01/20/2009) Corrine to call Braintree rug to look into replacing torn rug in basement.

(03/17/2009) AJ Rose Carpets will look at the problem this week. MA to ask them for a recommendation to possibly tear out that section of the carpet and replace it, or cover it with a “throw” type carpet matt.

(05/19/2009) Dave Modica is investigating.

(06/16/2009) Same.

(08/18/2009) Same.

Tuesday, October 28, 2008

October 21 Meeting

Attending:
Corinne Getchell (MA) --Modica Associates
Yelena Chigirinskaya (YC) --Trustee, Queensberry Condominium Trust
Douglas McClennen (DM) --Trustee, Queensberry Condominium Trust
Bill Gentz (BG) --Trustee, Queensberry Condominium Trust
Distribute to:
Kristen Lipstreuer (KL) --Trustee, Queensberry Condominium Trust
David Sherf (DS) --Trustee, Queensberry Condominium Trust
107 Mail Room for general information
111 Mail Room for general information


Structural Needs Assessment Report
The masonry work is progressing well. C&P expects to complete the project 1st week of November. See David Modica’s report for detailed information. A sill in the courtyard was missed and will be replaced. Also a lentil on the 3rd floor, Queensberry Street side has a crack running straight through it, and needs to be brought to the attention of C&P.

Second Means of Egress
All bedroom windows were properly marked by their unit owners. MA met with Logan Grate, and the windows were measured. In total, 6 grids will be replaced by the association. An additional (7th) grid will be replaced at the request and expense of the unit owner. Logan Grate will provide the final prices for the grids to MA.

Damanged Bollards by the Dumpsters
On Saturday, 10/11/2008, at 9:10am KL witnessed a Waste Management truck back into the bollards, knocking one of them completely out of place. David Modica is in contact with WM enquiring if they will pay for the damage inflicted by their truck.

Window Replacement
Window replacement is complete, and all screens have been fixed. MA is still working with Hadco, the company that replaced 111-2 unit windows in order to get the money back that the association paid for the panning that had to be later removed.

107 Laundry Room Floor
Same.

Dead Tree in Front of 107
DM and BG have removed the polls.

New Business:

Bad Smell in 107
DM and BG again noticed a strong smell of the sewer in the morning hours in building 107. There is speculation that the smell is from the 107 laundry, or from sewage backing up in the morning rush. Unit 107-20a had to have the drain cleared, and during the procedure a camera was run down the drain. Our buildings are on 4 times/year drain clearing schedule. MA to let the board know next time the drain clearing work occurs, so that we can see if the time of the smell correlates to when the drain clearing is performed.

Carpet Cleaning
The board ok's carpet cleaning to be performed in the common areas. Item Complete.

Issues in the Monthly Financial Statement
The numbers on the header page do not correspond to the numbers in the actual statement. MA will speak to the accountant and will email the board with an explanation.

Moped in the Courtyard
A Vespa moped is locked to the bike rack in the courtyard, and is blocking the walk way. MA will put a sign on the Vespa, as well as post notices on the doors asking the owner to move it. If not moved in a week, the vehicle will be towed.

Locking in Oil Price
The board discussed whether or not to lock in the oil price. Because the matter is so important, the board wants all members of the board to vote (only 3 present at the meeting). MA will send email asking the board members to vote over email.

These minutes are written to Yelena’s best recollection. Please notify her of any discrepancies immediately.

Carpet Cleaning

(10/21/08) The board ok's carpet cleaning to be performed in the common areas. Item Complete.