Wednesday, September 16, 2009

September 15 Meeting

Attending:
Corinne Getchell (MA) --Modica Associates
Yelena Chigirinskaya (YC) --Trustee, Queensberry Condominium Trust
Douglas McClennen (DM) --Trustee, Queensberry Condominium Trust
Bill Gentz (BG) --Trustee, Queensberry Condominium Trust


Distribute to:
Kristen Lipstreuer (KL) --Trustee, Queensberry Condominium Trust
David Sherf (DS) --Trustee, Queensberry Condominium Trust
107 Mail Room for general information
111 Mail Room for general information

Second Means of Egress
Logan Grates has been given the go ahead and is in the process of making the grates. They will be in touch with MA when the grates are ready for installation.

Window Replacement
MA sent another letter to Hadco Window and Door on 9/3, but has not had a reply.

107 Laundry Room Floor
Vogt & Company (the carpentor/vendor whose proposal the association is considering) warns that roll-out/linoleum type floor is pourous, and if there are leaks, the floor maybe severely damaged or destroyed. The carpenter discussed the issue with Dave Modica, and both recommend installing tiled floor. DM estimates that the price difference between tile and linoleum may be over $1000, and the linoleum floor should last for several years. MA to get an estimate on both tile floor and linoleum floor to see what the actual cost may be and what the actual difference in price is. Plumbing is to be inspected when the floor is removed. DM requests that the material to be used for the subfloor is specified in the proposal.

Deformation Monitoring Points (DMPs)
Work has been completed. MA has the report, and the board has reviewed it. MA to ask David Modica to determine when the next time should be for checking the DMPs--two years, or possibly 6 months/1 year for the new DMPs.

2008 Financials
DM would like the cash flow report, sent out to the owners, to show clearly why the association experienced the net loss even though the income from the temporary fee increase collected more money than required for the masonry repairs. DM will email the changes to MA, and MA will mail the information to the owners.


Jim, BG and Corinne will work together to correct the 2009 cash flow report, but will not hold up the mailing to the owners for that.

Torn carpet in basement
Same.

Landscaping
The proposal has been submitted to MA for the board to review. Currently, one Emerald Arborvitae plant in front of the 107 laundry vent is not healthy, probably due to vent, so replacing it, as the proposal suggests, will not resolve the issue. MA to ask the landscaper how that problem can be resolved.


The cost of the materials and labor proposed is $2000. Due to lack of finances to do this work right now, MA to ask the landscaper if the work can be postponed till next spring.

111 Laundry Sink Tap Is Leaking
The threads on the tap are stripped, so the facet handles have to be replaced. Dave Modica estimates the cost to be $200-$250.

Terrazzo Sidearms Need Repairs
107 sidearms are crumbling and falling apart. 111 sidearms also have problems, but are not in as bad shape as 107.


Miscellaneous:
  • Extra lentil sitting in the courtyard. MA to ask Chicorelli about it. It should probably not be left there, and should at least be moved down to the boiler room for safe storage.
  • Outer door glass been broken in 107. The glass needs to be replaced.
  • Front doors needs polish

These minutes are written to Yelena’s best recollection. Please notify her of any discrepancies immediately.

Tuesday, September 15, 2009

Terrazzo Sidearms Need Repairs

Previous work on the terrazzo side arms: Seal the Terrazzo Sidearms

(09/15/09) 107 sidearms are crumbling and falling apart. 111 sidearms also have problems, but are not in as bad shape as 107.

(08/17/2010) Chiccarelli and Pires has estimated repairs of the sidearms at $1,600.00 with the additional costs of permits.  The board has reviewed the bid and approved it.  MA to schedule the work sometime before November.

Monday, September 14, 2009

August 18 Meeting

Attending:

Corinne Getchell (MA) --Modica Associates
Yelena Chigirinskaya (YC) --Trustee, Queensberry Condominium Trust
Douglas McClennen (DM) --Trustee, Queensberry Condominium Trust
Bill Gentz (BG) --Trustee, Queensberry Condominium Trust

Distribute to:
Kristen Lipstreuer (KL) --Trustee, Queensberry Condominium Trust
David Sherf (DS) --Trustee, Queensberry Condominium Trust
107 Mail Room for general information
111 Mail Room for general information


Second Means of Egress
Samples have been delivered to Modica, and the board approves the samples. MA to call and schedule the installation.

Window Replacement
Same.

107 Laundry Room Floor
Carpenter (Vogt & Company) did a proposal and submitted to MA, with the cost of $7600. The proposal includes carpentry, but does not include tiling, removing and reinstalling the washing machines. The laundry company will have to do the removal and reinstallation of the machines. The laundry company will not give the association more than $700-800. The estimate is approximately $52.77/sq. foot (based on 8x18 ft area).

Doug proposes to just fix the floor, and put down rolled goods. Currently the floor is a potential tripping hazard.

MA to ask the carpenter to price items 1-3 on the proposal, without preparing the floor for tiling (described in item 2), without new cabinets or counters, and without painting.

When the floor is lifted, it is likely that they will find rot in the joices. Joices will have to be replaced. This work would not be included in the estimate.

Deformation Monitoring Points (DMPs)
Doug spoke to Cullinan Engineering. We did not lose a lot of information. The work is not completely redundant. The measurements have to be done 3 times due to temperature variances. They have to do it 2-3 times to get an accurate measurement. Cullinan will invoice one time once the work is completed. The board approves the proposal. MA will contact Cullinan Engineering to proceed.

Bad smell in 107
Doug and Bill have not noticed the bad smell for awhile. Item complete.

2008 Financials
Bill met with MA’s accountant and redid the summary for 2008. Transfer from reserve and other expenses items have been cleaned up, and the totals have changed as a result. Bill proposes to add footnotes when the new financial summary is sent to the owners. MA will put the new financial summary in a digestable form for the owners. Bill created a summary of income and expenses for the masonry project. The following will be mailed to the owners: reconciliation of 2008 financial summary with the footnotes, the masonry project summary, and trustee voting forms.

Torn carpet in basement
Same.

Landscaping
The landscaper is still working on the proposal.

Security cameras
Doug did some investigation on the cameras, and found that the association can get 5 WiFi cameras for about $500. Anyone can access the cameras if he/she knows the IP address and the password. The ongoing cost would be electricity and IP address. This is not a high priority, so the item will be moved to the Long Term projects list. This project may be coupled with redoing the front doors.

111 Laundry Sink Tap Is Leaking
Same.

These minutes are written to Yelena’s best recollection. Please notify her of any discrepancies immediately.